Procurement Act 2023 — what the first case means for automatic suspensions

We outline what's changed under the new test and consider what this may mean in practice for both contracting authorities and challengers.
We make the difference. Talk to us: 0333 004 4488 | hello@brabners.com
AuthorsPaddy FearnonAndreas PetrouMichael Winder
6 min read

The first judgment under the Procurement Act 2023 (the Act) has now been handed down in Parkingeye Limited v Velindre University NHS Trust & Anor [2026] EWHC 1019 (TCC), which provides clarity on how courts will approach applications to lift automatic suspensions on contract awards.
In reaching its decision, the Court applied for the very first time the new test found in section 102(2) of the Act. In doing so, the Court upheld the suspension.
Under the previous regime, courts frequently lifted suspensions. However, this decision suggests that a different approach may be taken under the Act.
Here, Paddy Fearnon, Andreas Petrou and Michael Winder from our specialist public procurement team outline what's changed under the new test and consider what this may mean in practice for both contracting authorities and challengers.
Where a legal challenge is made against a decision to award a public contract within the applicable standstill period (and the contracting authority is made aware of that claim), s.101 of the Procurement Act says that the contracting authority is automatically suspended from entering into the relevant contract until resolution of the claim.
This automatic suspension is only lifted through an order of the court following a legal application by the contracting authority to lift the suspension.
Under the Public Contracts Regulations 2015, the courts applied the American Cyanamid test when deciding whether to lift an automatic suspension. An essential aspect of that test was whether damages would be an adequate remedy for the claimant (i.e., in substitution of being awarded the relevant contract).
This meant that suspensions were lifted in a significant majority of reported cases, since damages were often found to be a sufficient remedy for the claimant.
In the recent Parkingeye case, the Court confirmed that the test for lifting the suspension present in s.102 of the Act is different in both method and effect from the previous regime, stating: “the new test is intended to be substantively and not merely formally very different, in both its method and its effect, from the former test”.
In assessing whether to lift the suspension, section 102 requires the court to have regard to three matters:
The Judge commented that, in general, the text of the Act showed that the public interest will generally tend to favour maintaining the suspension. The intention behind this is that it ensures public contracts are awarded in accordance with the law and suspensions aren’t lifted too lightly. That said, the Court did note that the facts of each case may weigh public interest differently.
Importantly, the public interest in lifting a suspension focuses on the provision of services themselves, rather than who provides them.
In practice, this means that a new contract that just delivers minor improvements, efficiencies or better value for money will likely carry limited weight. Where services are already being provided under an existing contract, this may weigh in favour of maintaining the suspension, since there remains continuity of services.
In the Parkingeye case, the car park management services were already being delivered by the incumbent provider and weren’t considered to be materially less beneficial than those under the proposed new contract. This supported the decision to maintain the suspension, pending resolution of the challenge.
In so far as the adequacy of damages, it’s now only one of several factors to take into consideration — rather than a ‘hurdle’ that claimants must pass.
Even where damages are considered to be an adequate remedy — which the Judge did in fact decide was the position in the Parkingeye case — the court will still undertake a broader balancing exercise (including the public interest and other relevant considerations) in determining whether a suspension should be lifted.
This is the first time that the Court has applied the new automatic suspension test under the Act. Under the previous regime, contracting authorities could reasonably expect their applications to lift suspensions to succeed due to damages being an adequate remedy for suppliers.
If this new approach is followed more widely, it may have a significant impact on procurement challenges going forward. Contracting authorities will need to be prepared for greater difficulties in lifting suspensions, particularly where incumbent arrangements can continue and new contracts are only delivering marginal benefits. A more exacting, evidence-based approach will be required.
Also, if more challenges are likely to proceed to full trial without the lifting of the suspension, contracting authorities may need to consider the impact of potential litigation delay and reflect this in their procurement planning and documentation.
We may see a requirement for existing service provisions to continue beyond their intended expiry dates, which may necessitate contract variations and extensions.
On the plus side, this recalibration of the automatic suspension as a stronger remedy may give suppliers a much-needed tool to better protect their positions earlier in a procurement challenge.
Overall, it demonstrates that the Procurement Act 2023 is a change from the previous EU-based regime and reminds all practitioners to consider the Act first (as opposed to perceived wisdom or even the guidance) when considering the legal framework that controls public procurement.
Finally, it’s important to note that the position adopted by the High Court in the Parkingeye case may be subject to further refinement and development, since the judgment refers to the potential for appeal. We’ll report on any future developments as they come to fruition.
If you’re preparing for a tender, involved in a procurement challenge or looking to disapply an automatic suspension, it’s important to understand how the courts may approach automatic suspensions.
Our procurement lawyers advise both contracting authorities and suppliers on public procurement (including public procurement challenges), the Procurement Act 2023 and procurement governance.
Book a meeting with us today to discuss how these changes affect you, as well as how best to prepare for upcoming guidance.
Talk to our procurement solicitors by calling 0333 004 4488, emailing hello@brabners.com or completing our contact form.
Paddy Fearnon
Paddy is a Trainee Solicitor in our commercial and intellectual property team.
Read more
Andreas Petrou
Andreas is an Associate in our commercial and intellectual property team. He leads our games and interactive entertainment team.
Read more
Michael Winder
Michael is a Partner in our commercial team. He leads our public procurement team.
Read more
Loading form...

We outline what's changed under the new test and consider what this may mean in practice for both contracting authorities and challengers.

We outline the key reforms and what contracting authorities and suppliers should be doing to prepare.

We explore the new Order that gives local authorities a new ability to shape below-threshold procurement markets in ways that were previously off-limits.

We explore the upcoming changes introduced by the Procurement Act 2023, when they take effect and what they mean for contracting authorities.

We explore how contracting authorities must approach contract variations under the Procurement Act 2023.

We explore the new minimum financial thresholds that will apply to public contracts and the application of the Procurement Act 2023 from 1 January 2026.

Just months after the Procurement Act 2023 came into force, a new consultation signals further wide-ranging reforms — with major implications for SMEs, local jobs and national resilience.

The 2025 Spending Review marks a pivotal shift in the UK’s fiscal and industrial strategy, with significant ramifications for companies operating in the health, science & technology and defence sectors.

Under the Procurement Act, large contracting authorities can be required to publish a Pipeline Notice on the Government’s ‘Find a Tender’ online service.

Here, experienced procurement lawyer Michael Winder offers his top tips for how to manage PFI contract expiries.

Our procurement lawyers recap the changes introduced by the Procurement Act 2023 which all contracting authorities and companies must comply with.

We highlight the key legal themes arising from the Grenfell Report's recommendations that you need to know about.

The Procurement Act 2023 has been delayed by four months and will now commence on 24 February 2025. Here's four practical steps for contracting authorities.

Explore the new requirements for publishing notices under the Procurement Act and the principles of transparency that underpin them.

It’s important for contracting authorities and bidders to understand the remedies available under the Procurement Act 2023 ahead of February 2025.

We examine the direct award of public contracts and what has changed under the Procurement Act ahead of its implementation in February 2025.

We explain the Procurement Act's reduction in procurement routes available to contracting authorities in favour of fewer, more flexible, procedures.

March 2024 was a busy month in the world of public procurement law, with a number of developments.

How will the Procurement Act’s objectives replace existing procurement principles? Our commercial law team explores.

The current public procurement regime is being replaced this year following the UK’s departure from the EU.

Here, our procurement law team explores what this Court of Appeal judgment means for procurement professionals.

Contracting authorities should be mindful of remaining up to date with case law and processes under the Regulations.

Until the Procurement Act 2023 comes into effect, the American-Cyanamid test continues to be used.

New minimum financial thresholds will apply to public procurement law from 1 January 2024.

The Procurement Act 2023 finally received Royal Assent on 26 October 2023. What comes next?