High Court dismisses challenge to the National Lottery procurement — key lessons & takeaways

We explore the Court’s reasoning, the key findings and what this judgment means for future procurement challenges.
We make the difference. Talk to us: 0333 004 4488 | hello@brabners.com
AuthorsSamantha ThompsonMichael Winder
6 min read

Image credit: Tosh Lubek, stock.adobe.com
Described by the High Court as “the most financially significant procurement process in UK history”, the decision in The New Lottery Company Ltd v The Gambling Commission was handed down in April 2026.
The dispute arose from the contested procurement process for the Fourth National Lottery licence (the Licence) and the steps taken by the Gambling Commission (the Commission) to implement that award, with the New Lottery Company Limited and Northern & Shell Plc (the Claimants) challenging both:
Here, Samantha Thompson and Michael Winder from our procurement team explore the Court’s reasoning, the key findings and what this judgment means for future procurement challenges.
A competitive process was run under the Concession Contracts Regulations 2016 (CCR 2016) to award a ten-year licence to operate the UK National Lottery. Four bidders reached the final stage and Allwyn Entertainment Ltd (Allwyn) was selected as the Preferred Applicant and Camelot selected as the Reserve Bidder. The Claimants ranked third after failing to meet over half of the mandatory criteria.
The Claimants brought two claims:
It was found that the Claimants “failed to make out any case of manifest error on the part of the Commission in their process claim” and that the modifications “were not substantial in that they did not change the economic balance in favour of Allwyn”. The Court further stated that the Claimants failed to establish that any breach caused them to suffer a loss. Furthermore, the modifications claim was time-barred so it would’ve failed regardless.
The Court reaffirmed that contracting authorities are granted a wide margin of discretion when evaluating bids, particularly in technically complex or high-stakes procurements.
It’s important to note that the Court’s role in this case wasn’t to determine whether it would’ve scored bids differently but whether the Commission’s decisions were:
The judgment emphasises that manifest error is a high bar to meet and to successfully challenge on that basis, the Claimants should’ve evidenced a clear and material error in the evaluation process, not simply that a plausible alternative interpretation of its bid could’ve been reached.
The Claimants argued that they’d been failed based on undisclosed criteria, including concepts such as “unaffordable levels of play”. The Court rejected this claim and held that evaluation criteria must be sufficiently clear for the “reasonably well-informed and diligent tenderer” but it doesn’t have to spell out every consideration that may inform an evaluator’s judgement.
The Claimants’ challenge placed emphasis on the alleged inadequacies of the Phase One feedback, arguing that the Claimants weren’t warned about issues that later led to the failure of their bid.
The Court found that first and foremost, the Commission’s feedback was in fact extensive and informative. However, feedback isn’t required to identify every weakness or potential reason for failure, particularly where a bidders own submission lacked detail.
In respect of the modifications claim, the Claimants argued that delays to implementing the contract, revised milestones and a potential extension to the licence fundamentally altered the contract.
While it was held that the changes were driven by exceptional litigation risk and transition difficulties caused by earlier litigation regarding the procurement of the licence, they didn’t alter the economic balance in Allwyn’s favour. Further, such modifications wouldn’t have resulted in a different winning bidder had they been known at the start.
The Court rejected the Claimants’ interpretation of Regulation 43 of CCR 2016, noting that contracting authorities are permitted to respond pragmatically where circumstances demand. In this case, the Court accepted that litigation risk and transition disruption were foreseeable considerations.
While this case relates to the previous legislation (specifically the CCR 2016), the points raised are still relevant and provide guidance for both contracting authorities and bidders alike.
Ultimately, a key feature throughout the judgment is the Court’s reliance on documentary evidence relating to moderation rationales, evaluation notes, internal risk trackers and contemporaneous emails. It was these documents that provided the Court with the evidence needed to make its judgment in favour of the Commission, demonstrating that clear records and audit trails remain one of the most effective shields against procurement challenges.
Our specialist procurement team can assist you with any support you may require in respect of procurement law, including if you wish to raise a challenge — or are defending a challenge — to a procurement process.
Talk to our procurement solicitors by calling 0333 004 4488, emailing hello@brabners.com or completing our contact form.

Michael Winder
Michael is a Partner in our commercial team. He leads our public procurement team.
Read more
Loading form...

We explore the Court’s reasoning, the key findings and what this judgment means for future procurement challenges.

We outline what's changed under the new test and consider what this may mean in practice for both contracting authorities and challengers.

We outline the key reforms and what contracting authorities and suppliers should be doing to prepare.

We explore the new Order that gives local authorities a new ability to shape below-threshold procurement markets in ways that were previously off-limits.

We explore the upcoming changes introduced by the Procurement Act 2023, when they take effect and what they mean for contracting authorities.

We explore how contracting authorities must approach contract variations under the Procurement Act 2023.

We explore the new minimum financial thresholds that will apply to public contracts and the application of the Procurement Act 2023 from 1 January 2026.

Just months after the Procurement Act 2023 came into force, a new consultation signals further wide-ranging reforms — with major implications for SMEs, local jobs and national resilience.

The 2025 Spending Review marks a pivotal shift in the UK’s fiscal and industrial strategy, with significant ramifications for companies operating in the health, science & technology and defence sectors.

Under the Procurement Act, large contracting authorities can be required to publish a Pipeline Notice on the Government’s ‘Find a Tender’ online service.

Here, experienced procurement lawyer Michael Winder offers his top tips for how to manage PFI contract expiries.

Our procurement lawyers recap the changes introduced by the Procurement Act 2023 which all contracting authorities and companies must comply with.

We highlight the key legal themes arising from the Grenfell Report's recommendations that you need to know about.

The Procurement Act 2023 has been delayed by four months and will now commence on 24 February 2025. Here's four practical steps for contracting authorities.

Explore the new requirements for publishing notices under the Procurement Act and the principles of transparency that underpin them.

It’s important for contracting authorities and bidders to understand the remedies available under the Procurement Act 2023 ahead of February 2025.

We examine the direct award of public contracts and what has changed under the Procurement Act ahead of its implementation in February 2025.

We explain the Procurement Act's reduction in procurement routes available to contracting authorities in favour of fewer, more flexible, procedures.

March 2024 was a busy month in the world of public procurement law, with a number of developments.

How will the Procurement Act’s objectives replace existing procurement principles? Our commercial law team explores.

The current public procurement regime is being replaced this year following the UK’s departure from the EU.

Here, our procurement law team explores what this Court of Appeal judgment means for procurement professionals.

Contracting authorities should be mindful of remaining up to date with case law and processes under the Regulations.

Until the Procurement Act 2023 comes into effect, the American-Cyanamid test continues to be used.

New minimum financial thresholds will apply to public procurement law from 1 January 2024.