The Times Best Law Firms

We're thrilled to have been commended in three separate categories in The Times Best Law Firms 2026.
Read more
We make the difference. Talk to us: 0333 004 4488 | hello@brabners.com
AuthorsVictoria TrigwellSamantha Thompson
6 min read

As we approach the anticipated new procurement regime in February 2025, it’s important for contracting authorities and bidders to understand the remedies available under the Procurement Act 2023 (the Act).
Here, our public procurement specialists Victoria Trigwell and Samantha Thompson take a look at the remedies set out in the Act and how they differ to those under the existing legislation.
In essence, not much. Although some of the language has changed, the basis of the remedies found in the existing regime have been replicated in the Act.
Nevertheless, it’s important to understand how the available remedies are presented under the Act and how this will impact different parties.
If a supplier wishes to apply for an automatic suspension of a contract, they must bring proceedings and notify the contracting authority during the applicable standstill period.
This differs to the current time limit which requires suppliers to bring such proceedings before the contract has been entered into.
Section 102 of the Act broadly replicates the equivalent provisions of the existing regulations except that it also allows for an order to suspend a contract modification from being entered into or performed.
It also sets out a new test that the court must apply when determining whether to make an interim order, which will replace the American Cyanamid test that is currently applied. Under the new test, the court must have regard to the public interest — in particular, that contracts should be awarded and modified in accordance with the law and avoiding delay in the supply of the goods, services or works.
The court must also have regard to the interests of suppliers including whether damages are an adequate remedy for the claimant and any other matter that the court considers appropriate.
Section 103 sets out the pre-contractual remedies available to economic operators.
Where the court is satisfied that a contracting authority’s decision or action has breached one of its enforceable duties — and the contract or contract variation (where relevant) has not yet been entered into — the following remedies are available.
Section 104 sets out the post-contractual remedies available to economic operators.
Where the court is satisfied that a contracting authority’s decision or action has breached one of its enforceable duties — and the contract or contract variation (where relevant) has been entered into — the following remedies are available:
Under section 105 of the Act, the grounds for setting aside a contract (referred to as the ‘set aside conditions’) are met if the court is satisfied that the claimant was denied a proper opportunity to seek a pre-contractual remedy because:
The set aside order effectively replaces the declaration of ineffectiveness under the current regime and the above conditions are similar to the existing grounds for ineffectiveness. However, it is a wider remedy than the declaration of ineffectiveness with emphasis upon ensuring that a claimant has a remedy in circumstances where it was denied a proper opportunity to seek a pre-contractual remedy.
There is also no requirement for the court to impose a fine on the contracting authority (which is a requirement under the declaration of ineffectiveness remedy in the existing regime).
A supplier must commence proceedings for an order to set aside a contract before the earlier of:
For other proceedings, there is a 30-day limitation period from the date when the supplier knew or ought to have known about the circumstances giving rise to the claim.
The court can order an extension of the time limit for bringing a claim, but this can’t extend to commencing proceedings after the six-month period in the case of an order to set aside a contract, nor in any case to extend beyond the period of three months from when the supplier first knew or ought to have known about the circumstances giving rise to the claim.
While the language in the Act differs slightly, contracting authorities and bidders alike should be familiar with these time limits from the existing regime.
Overall, while there is a change in language in relation to the remedies and the tests to be applied by the court and the powers of the court in relation to the remedies are slightly wider, the remedies under the Act remain largely the same as those in the current regime.
If you have any queries about remedies under the existing or new procurement regimes, please contact a member of our procurement team.
Talk to us by completing the contact form below.


Loading form...

We're thrilled to have been commended in three separate categories in The Times Best Law Firms 2026.
Read more

Our litigation team achieved a successful outcome for Docutech Office Solutions Ltd in a major claim against a former employee and his new employer.
Read more

We explore the potential impact of AI on existing copyright laws and delve into the other IP and cross-border issues that arise from the use of global AI tools.
Read more