Brabners secures favourable policy construction judgment for Acasta

Our award-winning litigation team has secured a High Court judgment in favour of Acasta European Insurance Company Limited.
Read more
We make the difference. Talk to us: 0333 004 4488 | hello@brabners.com
AuthorsJennie Jones
6 min read

The case of VMA Services Ltd v Project One London Ltd [2025] EWHC 1815 (TCC) acts as a further reminder to those seeking to determine the true value of interim payment applications that you must pay any Notified Sum first before referring a true value dispute to adjudication.
Here, Jennie Jones from our construction team looks at the background to the case, the legal issues it concerned and its practical implications for the construction law landscape.
VMA was a subcontractor appointed by Project One around October 2023 for mechanical works under a contract incorporating the JCT D&B Sub-Contract Agreement Conditions 2016. VMA submitted an Application for Payment No. 8 on 21 June 2024 in the sum of £106,434.88 (the Notified Sum) for works completed up to and including 30 June 2024. Project One failed to serve a valid Payment Notice or Pay Less Notice within the required timeframe.
In response, Project One referred a true value dispute to adjudication. VMA argued that the Notified Sum was due in full to VMA. Project One had failed to issue the required notices and thereafter failed to make payment of the Notified Sum — so VMA argued that Project One’s claim for true valuation should be dismissed. The adjudicator agreed and decided that the Notified Sum was due to VMA.
The court upheld the adjudicator’s decision on enforcement, confirming that where an adjudicator has found that sums are due to the responding party in circumstances such as these, the court can and will make an award of those sums to the responding party. A second adjudication to ‘rubber stamp’ the original decision and make an award isn’t required.
This decision underscores strict compliance with notice requirements in construction disputes and reinforces the ‘pay now, argue later’ principle, which mandates timely payments for work performed even if a dispute exists to maintain cash flow and prevent project disruption.
It’s well established through a plethora of caselaw adopting the underlying philosophy of adjudication (for example S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448, M Davenport Builders Ltd v Greer [2019] and AM Construction Ltd v The Darul Amaan Trust [2022] to name a few) that a paying party who hasn’t served a Payment Notice or a Pay Less Notice isn’t entitled to refer a dispute about the true value of a payment application to adjudication prior to making payment of the Notified Sum.
The argument on enforcement centred around whether the adjudicator had jurisdiction to make a monetary award in favour of VMA, the respondent to the adjudication.
The court was asked to balance two potentially conflicting principles of law. First, that a party isn’t able to make a monetary recovery arising from its defence. A cross claim raised by a responding party may offset sums otherwise owing but doesn’t arise as an independent claim for a monetary award. Second, that the overriding aim of the Housing Grants and Construction Regeneration Act 1996 (the Act) is to get payment flowing — so, parties should be required to pay first and argue later.
Adrian Williamson, sitting as Deputy Judge in The Technology and Construction Court (TCC), reviewed the relevant case law and held that:
This decision firmly applied and reinforced the ‘pay now, argue later’ principle at the cornerstone of adjudication and a core tenet of Part II of the Act. The court is generally uninterested in clever arguments on jurisdiction. Where the adjudicator comes to a decision that a Notified Sum is due to the responding party, the court can perfect that decision by making the necessary award.
This case has real practical implications for both employers and main contractors (payers):
While VMA Services v Project One isn’t a traditional ‘smash and grab’ adjudication, it is a stark reminder that 'smash and grab' principles apply even when raised as a defence. The case reinforces the importance of serving valid notices and the procedural sequencing of payment and adjudication.
You risk the responding party successfully bringing a ‘smash and grab’ defence, resulting in an adjudicator finding that the notified amount is due and owing to the responding party. The court has once again demonstrated its willingness to stand behind the ‘pay now, argue later’ principle.
Our construction team has extensive experience in navigating payment disputes, adjudication procedures and contract administration. We can help you to avoid costly missteps and protect your position.
Talk to us by giving us a call on 0333 004 4488, sending us an email or completing our contact form below.
Loading form...

Our award-winning litigation team has secured a High Court judgment in favour of Acasta European Insurance Company Limited.
Read more

We provide an overview of key construction law cases from 2025 and explore the practical implications and emerging trends that are shaping the industry.
Read more

Explore the legal and practical implications of the 'pay now, argue later' principle in construction disputes through the landmark case of VMA Services Ltd v Project One London Ltd.
Read more