Making Places Work — new study reveals the most improved places in the North of England

Our award-winning regeneration team has launched a new report that uncovers how life and work across the North of England has changed since the millennium.
We make the difference. Talk to us: 0333 004 4488 | hello@brabners.com
AuthorsJennie Jones
9 min read

The legal landscape for construction professionals, developers and associated entities has been transformed by the enactment of the Building Safety Act 2022 (BSA). Recent judgments from the Supreme Court, the Court of Appeal and the Technology and Construction Court (TCC) provide critical guidance on limitation periods, liability hierarchies, claims management and risk allocation.
These issues were at the forefront of discussions during our recent Building Links event — held on 27 November 2025 in our Manchester office — where Alexandra Bodnar of Keating Chambers expertly guided us through the pivotal cases of 2025 while explaining the practical implications and emerging trends that are shaping the industry.
Here, construction lawyer and the founder of the Building Links network, Jennie Jones, provides an overview of key cases from 2025 that you need to know about.
This dispute concerned structural design defects identified by BDW in two of its high-rise residential developments during 2019. Consulting engineer URS was responsible for the structural design. Although BDW had already sold the properties and any homeowner claims in relation to the defects would have been time-barred, BDW nevertheless undertook remedial works in 2020 and 2021 and subsequently sued URS to recover its costs. Following the introduction of the BSA and its extended limitation period, BDW successfully sought leave to add claims under the Defective Premises Act 1972 (DPA) and the Civil Liability (Contribution) Act 1978. After multiple hearings, the Supreme Court ultimately ruled in favour of BDW.
The Supreme Court reaffirmed the principle in Pirelli that negligence claims for latent defects accrue when defective elements are incorporated into the building, not when they’re discovered. This means that developers can’t rely on later discovery to restart limitation periods for such claims.
Section 135 of the BSA extends the limitation period retrospectively to 30 years for DPA claims accrued before 28 June 2022, enabling developers to pursue historic claims decades after completion of the works.
Developers who remediate defects voluntarily can still recover costs from those responsible. The Court emphasised that public policy encourages proactive remediation and developers shouldn’t be penalised for “doing the right thing”.
The Court also held that professional consultants owe duties under the DPA, extending statutory obligations beyond contractors. This broadens the pool of potential defendants from whom developers can seek recovery.
This judgment strengthens the position of developers seeking redress for historic defects and signals that consultants should review historic projects for potential liability exposure under the DPA.
This dispute concerned fire safety defects discovered at the Crown Heights residential development in Hampshire nearly 20 years post-completion. Basingstoke Property Company Limited (BPCL) engaged Ardmore to carry out the works, which were completed between 2003 and 2004. BPCL subsequently assigned its interests and rights under the contract to BDW. BDW alleged that Ardmore breached the building contract and Section 1(1) of the DPA. It relied on the extended limitation period under the BSA and referred the matter to adjudication. The adjudicator ultimately awarded BDW over £14m. Ardmore resisted enforcement, arguing (among other points) that the adjudicator lacked jurisdiction because the DPA claim was statutory and the adjudication clause only covered disputes arising “under this contract”, as well as that the process was unfair given Ardmore’s lack of documentation due to passage of time since completion which forced reliance on BDW’s evidence. However, the TCC rejected its objections and enforced the decision.
The TCC confirmed that adjudication is available for resolving historic defect claims under the DPA, thanks to the BSA’s extended limitation periods.
The judgment underscores the broad scope of adjudication clauses and the courts’ willingness to enforce adjudicators’ decisions, even in complex historic disputes.
This decision means that developers now have a powerful enforcement tool for historic safety claims through adjudication, reducing reliance on lengthy and expensive litigation proceedings. It also significantly alters risk profiles for contractors who should ensure strong project governance to deal with historic cladding claims.
This dispute concerned fire safety defects discovered in the external walls of five tower blocks in the former London 2012 Olympic Village at Stratford in November 2020. The estate was managed by East Village Management Ltd, which undertook major remediation works largely funded by the Building Safety Fund. Triathlon — which holds long leasehold interests in the social housing in the blocks — applied for Remediation Contribution Orders (RCOs) under Section 124 of the BSA to recover its share of the remediation costs and other costs incurred from the original developer of the estate (Stratford Village Development Partnership) and its parent company (Get Living plc). The First-tier Tribunal granted the orders. The parties appealed but were unsuccessful.
The Court of Appeal established that RCOs under Section 124 of the BSA can apply retrospectively covering costs incurred before 28 June 2022, even where public funding such as the Building Safety Fund is available.
It was deemed “just and equitable” to impose RCOs on developers and their associated entities, placing them at the top of the liability hierarchy.
Parent companies and associated entities — even if not involved in the original construction — can’t shield themselves behind thinly capitalised Special Purpose Vehicles to avoid liability.
Public funds are a last resort — not a substitute for developer responsibility.
This case demonstrates that corporate groups must anticipate liability exposure across their entire structure (including parent companies) and implement robust governance and financial planning to meet potential remediation obligations.
Section 149 of the BSA introduces a new statutory cause of action against manufacturers and suppliers of cladding products for past defaults with a limitation period of 30 years for claims arising before 28 June 2022 and 15 years thereafter.
Claimants must satisfy four conditions:
Despite the broad drafting of this provision, proving all four conditions — especially causation — will be challenging.
We expect to see a rise in claims being brought against manufacturers and suppliers of cladding products. However, historic documentation gaps, complex causation chains and reliance issues mean that these cases will likely be fact-heavy, expert-driven and expensive to litigate.
This dispute concerned fire safety and other defects discovered at a high-rise residential complex in Cardiff, built by Redrow between 2004 and 2007. Forty-one leaseholders (including Mr and Mrs Wilson) sued HB (Redrow’s successor) for breach of contract and Section 1 of the DPA. Before trial, HB agreed with the management company to carry out a comprehensive programme of remedial works. As a result, no claims for remedial costs could be made. Also, the Wilsons submitted a Schedule of Loss containing nine heads of loss not in accordance with those pleaded in their particulars of claim. The TCC struck out seven of these losses as too remote, unclear or speculative. The Wilsons appealed but were unsuccessful.
The Court of Appeal confirmed that claimants can’t introduce new claims under a separate "Schedule of Loss" — any new head of loss must be properly pleaded and particularised in the statement of case.
Losses are to be clearly pleaded and evidenced as any speculative losses — such as claims for investment losses and tax planning in this case — will be struck out.
The Court also held that if developers agree to remediate at no cost, claimants can’t recover the costs of those works. Only residual “blight” (post-remediation diminution in value) may be recoverable.
This decision narrows the scope of recoverable damages where developers agree to remediate defects. The judgment also strictly reinforces the importance of proper pleading standards in construction defect cases. It emphasises that damages claims must be clearly particularised in the initial pleadings and that subsequent documents (like a Schedule of Loss) can’t be used to introduce new claims.
This dispute concerned risk allocation for existing structures under a heavily amended JCT Design & Build 2016 contract. Capital & Centric engaged Sisk to construct new residential buildings and repair two listed mills at Weir Mill, Stockport. Clause 2.42 placed the risk of existing structures on Sisk but Item 2 of the “Contract Clarifications” (in both electronic and hard copy versions) required the Employer to insure the existing buildings and obtain a warranty, suggesting Employer risk. The electronic version also included a “Tender Submission Clarifications” worksheet implying Capital & Centric didn’t accept the risk during negotiations, creating inconsistency.
The Court ruled in favour of Sisk, holding that Item 2 (Employer Risk) overrode the general risk allocation clauses. Inconsistencies were resolved in favour of the signed hard copy.
Only documents expressly incorporated into the contract have legal effect — pre-contract clarifications and tender notes in electronic bundles can’t influence interpretation.
This case serves as a reminder for parties to ensure that their risk allocation provisions are clear and internally consistent and that all versions of documents (such as electronic and hard copy) are identical to avoid costly litigation.
Building Links is a networking group for construction and property professionals. Each quarter, we bring together leading voices to discuss and demystify the key issues that affect the industry — providing members with essential guidance on how to navigate challenges and capitalise on opportunities.
These exclusive, invite-only events focus on education, collaboration and sharing best practice. They also present a great opportunity to network with peers in a welcoming and friendly environment.
Find out more and join the network.
Our experienced construction lawyers use decades of expertise to provide proactive, commercially focused support across all aspects of construction services to protect your interests and mitigate risk throughout the lifecycle of a project.
Talk to our experts today by giving us a call on 0333 004 4488, sending us an email or completing our contact form below.
Loading form...

Our award-winning regeneration team has launched a new report that uncovers how life and work across the North of England has changed since the millennium.

Our award-winning litigation team has secured a High Court judgment in favour of Acasta European Insurance Company Limited.

Explore the legal and practical implications of the 'pay now, argue later' principle in construction disputes through the landmark case of VMA Services Ltd v Project One London Ltd.

The UK’s housing sector in 2025 is undergoing major shifts, with Government reforms aiming to boost supply and affordability.

The construction sector is at a turning point. With tighter regulations, better awareness and clear data, health and safety is being seen as an investment in people and the bottom line.

Events from three of our growing invite-only networking groups will take place between July and September this year in Lancashire.

We explore the economic case for regeneration and outline three key areas that can help to get deals done and accelerate progress.

The key legal considerations for clubs looking to install artificial pitches — from complying with pitch standards to construction contracts and more.

Our latest Building Links event explored how AI is being used in construction as well as the challenges and misconceptions that come with its use.

There are key charity law requirements and property law considerations to be aware of before a charity purchases land. Our lawyers explore.

We explore the legal and commercial considerations that underpinned the successful sport-led regeneration scheme for Bramley-Moore Dock and Liverpool Waters.

The Government has revamped the National Planning Policy Framework (NPPF) to pave the way for the delivery of 1.5m new homes over the next five years.

As a ‘Client’, you must make suitable arrangements for planning, managing and monitoring your project to ensure compliance with the Building Regulations.

What key factors are responsible for the construction skills gap? Here, Jennie Jones in our construction team explores key factors and what industry leaders can do to take action and meet growing demand.

A recent case underscores the importance of exclusive possession in determining whether an agreement around property creates a lease or a licence.

Here, Claudia Sivori explains how prosecutions will be brought on corporate manslaughter and Director’s duties following the Phase 2 Grenfell Report findings.

Ibrahim Ibrahim, Managing Director of Portland Design and author of ‘Future-ready Retail’ considers how consumers are changing and the way in which the high street is responding.

We highlight the key legal themes arising from the Grenfell Report's recommendations that you need to know about.

Our property litigators consider the recent developments in newcomer injunctions and how that was dealt with in Upholland.

Our construction law experts explore key changes to the JCT suite of contracts for 2024 and asks — does it go far enough?

Our construction law team explores the role of the new RBCA and how to determine which regime a construction project should operate under during the transition period.

Our construction lawyers provide an overview of the Accountable Person and Principal Accountable Person roles under the Building Safety Act 2022 and applicable secondary legislation.

Our construction law team explores the Supreme Court ruling in Abbey Healthcare v Augusta 2008 and what it means for contractors and beneficiaries in the construction industry that rely on collateral warranties.

An overview of the Building Safety Regulator's new change control regime and associated requirements for construction projects.

Explore the landmark judgment which found that continuing to fly a drone over private property amounted to trespass with the legal team that secured the judgment.